340:110-3-97(d)(3) | Smoke detectors are tested monthly and a record of the date is documented. | Smoke detector tests were last documented on 3/12/19 | The tests will be documented when they are completed each month. | 07/31/2019 | No |
340:110-3-97(e)(2) | Carbon monoxide detectors are tested monthly and a record of the date is documented. | Carbon monoxide detectors were last documented on 3/12/19 | The tests will be documented when they are completed each month | 07/31/2019 | No |
340:110-3-86.1(n) | Drills. Drills are conducted and follow the pre-determined emergency plans and procedures. A record of drills is maintained at the home. | Fire and tornado drills have not been documented since 3/12/19 | The drills will be documented when they are completed each month | 07/31/2019 | No |